What is the maximum recommended duration for a Sprint?
A. 2 weeks
B. 1 month
C. 3 weeks
D. 4 weeks
Correct Answer: B
The Scrum Guide recommends a maximum Sprint duration of one month. However, shorter Sprints, such as 1 or 2 weeks, are more common as they allow for more frequent inspection and adaptation