    What is the purpose of a Sprint Review?

     

    A. To take time to judge the validity of the project

    B. To inspect the product Increment with the stakeholders and collect feedback on next steps

    C. To review the Scrum Team’s activities and processes during the Sprint

    D. To build team sprint

     

    Correct Answer: B

    A sprint review is a meeting held at the end of a sprint, during which the team shows what was accomplished, while the stakeholders provide feedback. The Sprint Review is an event that is time-boxed to 4 hours or less for a one-month Sprint. It’s also the only Sprint event where stakeholders are invited

    It’s a collaborative working session rather than a one-sided presentation that is meant to create and Inspect and Adapt opportunity for the Scrum Team. The Scrum team shows what is “Done”, gets feedback and then they can adapt. This should result in a revised Backlog for the next Sprint

     

    Want to learn more about Scrum Events? Read our Blogpost ! https://scrumrevolution.com/the-basics-scrum-events/