What is the recommended size for the Product Backlog items?
A. One day’s work for the Development Team
B. One week’s work for the Development Team
C. Two weeks’ work for the Development Team
D. One month’s work for the Development Team
Correct Answer: A
The Product Backlog items should generally be small enough to be completed by the Development Team within one day. Smaller items provide more clarity and allow for better planning and progress tracking