    What should the Scrum Team do if they find that their capacity is insufficient for the work in the Sprint?

     

    A. Add more items to the Sprint Backlog to match the capacity

    B. Extend the Sprint duration to accommodate the additional work

    C. Collaborate with the Product Owner to adjust the scope of the Sprint

    D. Request the Scrum Master to find additional team members

     

    Correct Answer: C

    If the Scrum Team finds that their capacity is insufficient for the work in the Sprint, they should collaborate with the Product Owner to adjust the scope of the Sprint. The Product Owner can reprioritize the Product Backlog items or remove items from the Sprint to match the team’s capacity realistically