    When does a Developer become the sole owner of an item on the Sprint Backlog?

     

    A. Whenever a team member can accommodate more work

    B. At the Sprint Planning event

    C. During the Daily Scrum

    D. Never. All Sprint Backlog items are “owned” by the Developers on the Scrum Team

     

    Correct Answer: D

    A Developer never becomes the sole owner of an item on the Sprint Backlog, the Development team is jointly responsible for all items on the Sprint Backlog