When is a Sprint over?
A. When the Product Owner says it is done
B. When all Product Backlog items meet their definition of “Done”
C. When all the tasks are completed
D. When the time-box expires
Correct Answer: D
A Sprint has a pre-determined length, when this is over the next Sprint immediately follows the previous one