    Which are NOT appropriate topics for discussion in a Sprint Retrospective? (Choose all that apply)

     

    A. Definition of “Done”

    B. How the team does its work

    C. Team relations

    D. The value of work currently represented in the Product Backlog

    E. Arranging the Sprint Backlog for the next Sprint

     

    Correct Answer: E

    Arranging the Sprint Backlog belongs in the Sprint Planning session. As for the value of work currently represented in the Product Backlog, this is something the Product Owner decides with the stakeholders