    Which is not a Product Owner Responsibility

     

    A. Running the Daily Scrum meeting

    B. Gathering requirements for Product Backlog items

    C. Working with stakeholders to determine details about Product features

    D. Inspecting work at the Sprint Review

     

    Correct Answer: A

    Key responsibilities of the Product Owner are gathering requirements about Product Backlog items and working with Stakeholders to determine what the Product should look like. Running the Daily Scrum meeting is done by the Developers themselves