    Which of the following is required by Scrum?

     

    A. Sprint Retrospective

    B. Members must be stand up at the Daily Scrum

    C. Sprint Burn-down Chart

    D. Release planning

    E. All of the above

     

    Correct Answer: A

    Of the options offered, only the Sprint Retrospective is required