Which of the following may change during the Sprint?
A. Product Goal
B. Minimum level of quality
C. Sprint Backlog
Correct Answers: C
The Product Goal does not change often and is adjusted by the Product Owner and the stakeholders. So this would not change during the Sprint. The level of quality also does not change during the Sprint. This is defined in the Definition of “Done”. The Sprint Backlog can change since that is one of the principles of Agile working, you adjust when necessary.