    Which output from Sprint Planning provides the Development Team with a target and overarching direction for the Sprint?

     

    A. The Sprint Backlog

    B. The Sprint Goal

    C. The release plan

    D. Sprint Review minutes

     

    Correct Answer: B

    The Sprint Goal provides the Development Team with a target for the Sprint. It is the Product Backlog items selected for the Sprint, plus the plan for delivering them