    Which Scrum Artifact represents a comprehensive description of a new functionality or enhancement to be implemented in the product?

     

    A. Definition of Done

    B. Sprint Backlog

    C. Product Backlog

    D. Increment

     

    Correct Answer: C

    The Product Backlog is an ordered list of all the features, functionalities, enhancements, bug fixes, and other requirements that need to be implemented in the product. Each item in the Product Backlog represents a comprehensive description of a new functionality or enhancement that the Scrum Team may work on in future Sprints. The Product Owner is responsible for maintaining and prioritizing the Product Backlog