    Which Scrum Value is affected by a lack of trust in the Scrum Team?

     

    A. Focus

    B. Respect

    C. Openness

    D. Courage

    E. Commitment

    F. All of the above

     

    Correct Answer: F

    Scrum has 5 values, Focus, Respect, Openness, Courage and Commitment