Which statement best describes the Sprint Review?
A. It is used to congratulate the Development Team if it did what it forecast, or to punish the Development Team if it failed to meet its forecast
B. It is a demo at the end of the Sprint for everyone in the organisation to check on the work done
C. It is a mechanism to control the Development Team’s activities during a Sprint
D. It is when the Scrum Team and stakeholders inspect the outcome of a Sprint and figure out what to do next
Correct Answer: D
A sprint review is a meeting held at the end of a sprint, during which the team shows what was accomplished, while the stakeholders provide feedback. It’s a collaborative working session rather than a one-sided presentation