Which three of the following events are time-boxed in Scrum? (choose the best three answers)
A. Release Planning
B. Release Retrospective
C. Sprint Retrospective
D. Sprint Planning
E. Refinements
F. Daily Scrum
G. Testing
Correct Answer: C,D,F
The time-boxed events in Scrum are:
Sprint Review
Sprint Planning
Sprint Retrospective
Daily Scrum
Want to learn more about Scrum Events? Read our Blogpost ! https://scrumrevolution.com/the-basics-scrum-events/