    Which two things should the Development Team do during the first Sprint? (Choose two)

     

    A. Make up a plan for the rest of the project

    B. Analyze, describe, and document the requirements for the subsequent Sprints

    C. Develop at least one piece of functionality

    D. Analyze, design, and describe the complete architecture and infrastructure

    E. Create an increment of potentially releasable software

     

    Correct Answer: C, E

    According to Scrum, at least one usable Increment should be produced during each Sprint. This applies to all Sprint, also the first one.