    Who can abnormally terminate a Sprint?

     

    A. The Scrum Master

    B. The Development Team or its members

    C. The Product Owner

    D. The Stakeholders

     

    Correct Answer: C

    Only the Product Owner has the authority to terminate a Sprint, even though this should be avoided at all cost. The Scrum Master can terminate a Sprint only on the Product Owners behalf