Home Forums PSM1 Exam Questions and Awnsers Who creates a Product Backlog Item’s estimate?

  • This topic is empty.
Viewing 1 post (of 1 total)
  • Author
    Posts
  • #26619
    Scrum Revolution
    Keymaster

    Who creates a Product Backlog Item’s estimate?

     

    A. The Development Team after clarifying requirements with the Product Owner

    B. The Product Owner with input from the Development Team

    C. The most senior people in the organization, including architects and subject matter experts

    D. The Scrum Master

    E. The Development Team, alone

     

    Correct Answer: A

    After the requirements are clear the Development Team can estimate a Product backlog item. In Scrum this process is called Poker

Viewing 1 post (of 1 total)
  • You must be logged in to reply to this topic.