    Who is responsible for managing the Product Backlog?

     

    A. The Scrum Master

    B. The Product Owner

    C. The Development Team

    D. The stakeholders

     

    Correct Answer: B

    The Product Owner is responsible for managing the Product Backlog. They prioritize and maintain the items in the Product Backlog based on value and ensure that it is transparent and understandable to all stakeholders

     

    Want to learn more about Scrum Artifacts? Read our Blogpost! https://scrumrevolution.com/how-scrum-artifacts-are-in-fact-agile-documentation/