Home Forums PSM1 Exam Questions and Awnsers Who should make sure everyone on the Scrum Team does his or her tasks for the Sprint?

  • This topic is empty.
Viewing 1 post (of 1 total)
  • Author
    Posts
  • #26634
    Scrum Revolution
    Keymaster

    Who should make sure everyone on the Scrum Team does his or her tasks for the Sprint?

     

    A. The Project Manager

    B. The Product Owner

    C. The Scrum Master

    D. The Scrum Team

    E. All of the above

     

    Correct Answer: D 

    Scrum is based on self-organization so the whole Scrum Team should make sure everyone finishes his or her tasks

Viewing 1 post (of 1 total)
  • You must be logged in to reply to this topic.