Steven, the Scrum Master, observes a debate forming and members beginning to take sides. What is the best action for Steven to take?

During the implementation of an item in the Sprint Backlog, a conflict arises between team members about what work is needed to make the item ‘done’. Some say it is a part of the Definition of Done an...

In forum PSM2 Questions with Answers

7 months ago
What is the best action for a Scrum Master to take?

After several Sprints, a key stakeholder starts using the product. The stakeholder is surprised by the slow performance and complains to the Product Owner. The Product Owner comes to the Scrum Master ...

In forum PSM2 Questions with Answers

7 months ago
What are two good options for the Scrum Master? (Choose the best two answers)

Several Sprints into a project, the Product Owner tells the Scrum Master that a key stakeholder just started using the product. The stakeholder is unhappy with the quality of the product. What are tw...

In forum PSM2 Questions with Answers

7 months ago
Steven, the Scrum Master, observes that one of the Development Team members is not attending the Daily Scrum. The Development Team feels this is ok as they all sit in the same area and already have constant communication throughout the day. Which is

Steven, the Scrum Master, observes that one of the Development Team members is not attending the Daily Scrum. The Development Team feels this is ok as they all sit in the same area and already have co...

In forum PSM2 Questions with Answers

7 months ago
In Scrum, how would budgeting and financial forecasting be performed? (Choose two.)

In Scrum, how would budgeting and financial forecasting be performed? (Choose two.) A. Frequently inspect the outcomes of the delivered Sprint Increments to understand how much value is being produced...

In forum PSM2 Questions with Answers

7 months ago
Which three acceptable solutions would Steven consider? (Choose three)

Steven is a Scrum Master for three different teams building a single product from the same Product Backlog. Development Team members from each team have approached Steven complaining that their teams ...

In forum PSM2 Questions with Answers

7 months ago
What should Steven, the Scrum Master, do to solve this potential problem?

Three Development Teams are currently building a single product and pulling work from the same Product Backlog. All three teams have identified that they will need Dan, a database specialist, to work ...

In forum PSM2 Questions with Answers

7 months ago
In what two ways is velocity and technical debt related? (Choose two)

In what two ways is velocity and technical debt related? (Choose two) A. They are not related because technical debt is non-functional and velocity is calculated based on end user functionality.B. As ...

In forum PSM2 Questions with Answers

7 months ago
Which two actions are the most appropriate for Steven to take? (Choose two.)

Steven, the Scrum Master, is approached by one of the Development Team members saying that they are not completing regression tests for all of the work they are performing to the level defined in the ...

In forum PSM2 Questions with Answers

7 months ago
What factors may have led to this?

At the fifth Sprint Retrospective, the Product Owner mentions that he is surprised about the amount of technical debt that has built up in the system and that the product is not able to support an ade...

In forum PSM2 Questions with Answers

7 months ago
What are two good ways for Steven to address this problem? (Choose two)

Individual Development Team members have been approaching Steven, the Scrum Master, to complain about Chris. Chris has the most experience on the system they are building. He often questions the choic...

In forum PSM2 Questions with Answers

7 months ago
Of the choices raised by future team members, what would Steven encourage?

Of the choices raised by future team members, what would Steven encourage? Steven is a Scrum Master asked to assist in creating five new Scrum Teams that will be working to build a highly anticipated ...

In forum PSM2 Questions with Answers

7 months ago
What is the most effective way to recover?

Paul is a Product Owner for multiple products. Each product is allocated a dedicated Scrum Team and a set budget. Based on the average velocity of a previous product release, Paul had estimated a new ...

In forum PSM2 Questions with Answers

7 months ago
What would be two acceptable outcomes of the discussion? (Choose two.)

During the Sprint Review, the Product Owner decides to release the current Increment to production. The stakeholders suggest temporarily delaying the next Sprint in order to respond more quickly to us...

In forum PSM2 Questions with Answers

7 months ago
Scrum addresses which of the following four risks in software development? (Choose four.)

Scrum addresses which of the following four risks in software development? (Choose four.) A. The complexity and unpredictability of the requirements.B. The stability and complexity of the technology.C...

In forum PSM2 Questions with Answers

7 months ago