Currently, your Development Teams are organized to address a single layer only (for example, front end, middle tier, back end, and interfaces). What are three things to consider when deciding to move away from such component teams toward feature team

Currently, your Development Teams are organized to address a single layer only (for example, front end, middle tier, back end, and interfaces). What are three things to consider when deciding to move ...

In forum PSM1 Questions with Answers

7 months ago
As the Sprint Planning meeting progresses, the Development Team sees that the workload is greater than they can handle. Which two are valid actions? (Choose two.)

As the Sprint Planning meeting progresses, the Development Team sees that the workload is greater than they can handle. Which two are valid actions? (Choose two.) A. Recruit additional Development Tea...

In forum PSM1 Questions with Answers

7 months ago
Which of the following is the primary responsibility of the Scrum Master?

Which of the following is the primary responsibility of the Scrum Master? A. Managing the team's work B. Creating the product backlog C. Ensuring the team follows the Scrum framework D. Assigning task...

In forum PSM1 Questions with Answers

7 months ago
Who is responsible for managing the Product Backlog?

Who is responsible for managing the Product Backlog? A. The Scrum Master B. The Product Owner C. The Development Team D. The stakeholders Correct Answer: B The Product Owner is responsible for manag...

In forum PSM1 Questions with Answers

7 months ago
What is the recommended size for a Scrum Team?

What is the recommended size for a Scrum Team? A. 5-10 members B. 10-15 members C. 3-5 members D. It depends on the project size Correct Answer: A The recommended size for a Scrum Team is 5-10 membe...

In forum PSM1 Questions with Answers

7 months ago
During the Sprint Review, who presents the work done by the Scrum Team?

During the Sprint Review, who presents the work done by the Scrum Team? A. The Product Owner B. The Scrum Master C. The Development Team D. The stakeholders Correct Answer: C During the Sprint Revie...

In forum PSM1 Questions with Answers

7 months ago
In Scrum, who is responsible for making sure the Development Team has a clear and properly refined Product Backlog?

In Scrum, who is responsible for making sure the Development Team has a clear and properly refined Product Backlog? A. The Scrum Master B. The Product Owner C. The Development Team D. The stakeholders...

In forum PSM1 Questions with Answers

7 months ago
When does the Scrum Team hold the Sprint Retrospective?

When does the Scrum Team hold the Sprint Retrospective? A. At the end of each Sprint B. At the beginning of each Sprint C. Every month D. Only when the Product Owner requests it Correct Answer: A Th...

In forum PSM1 Questions with Answers

7 months ago
What is the maximum recommended duration for a Sprint?

What is the maximum recommended duration for a Sprint? A. 2 weeks B. 1 month C. 3 weeks D. 4 weeks Correct Answer: B The Scrum Guide recommends a maximum Sprint duration of one month. However, short...

In forum PSM1 Questions with Answers

7 months ago
What is the primary objective of the Sprint Review?

What is the primary objective of the Sprint Review? A. To demonstrate the completed Increment to stakeholders B. To inspect the progress of work during the Sprint C. To discuss the challenges faced by...

In forum PSM1 Questions with Answers

7 months ago
What is the primary purpose of the Sprint Retrospective?

What is the primary purpose of the Sprint Retrospective? A. To review and approve the Increment B. To inspect the Product Backlog and adjust priorities C. To inspect how the Scrum Team performed durin...

In forum PSM1 Questions with Answers

7 months ago
When should the Development Team's input be included in the Sprint Planning?

When should the Development Team's input be included in the Sprint Planning? A. After the Product Owner has finalized the Product Backlog B. Before the Product Owner creates the Product Backlog C. The...

In forum PSM1 Questions with Answers

7 months ago
In Scrum, what is the primary purpose of the Increment at the end of a Sprint?

In Scrum, what is the primary purpose of the Increment at the end of a Sprint? A. To demonstrate the product to stakeholders for feedback B. To have a potentially releasable version of the product C. ...

In forum PSM1 Questions with Answers

7 months ago
What should the Scrum Team do if they find that their capacity is insufficient for the work in the Sprint?

What should the Scrum Team do if they find that their capacity is insufficient for the work in the Sprint? A. Add more items to the Sprint Backlog to match the capacity B. Extend the Sprint duration t...

In forum PSM1 Questions with Answers

7 months ago
In Scrum, who is responsible for promoting self-organization within the Development Team?

In Scrum, who is responsible for promoting self-organization within the Development Team? A. The Scrum Master B. The Product Owner C. The Development Team D. The stakeholders Correct Answer: C The D...

In forum PSM1 Questions with Answers

7 months ago
Page 7 / 18