Forum

For which is the Sc...
 
Meldingen
Alles wissen

For which is the Scrum Master responsible

1 Berichten
1 Gebruikers
0 Reactions
91 Bekeken
(@roy-slotboom_pewjck65)
Berichten: 261
Lid Admin
Topic starter
 

For which is the Scrum Master responsible

A. Managing the performance of the Scrum Team
B. The meetings and the objectives that a Scrum Team sets for itself
C. The Scrum framework being adopted and used properly
D. Keeping track of resource allocation

Correct Answer: C

The Scrum Master is accountable for establishing Scrum as defined in the Scrum Guide. They do this by helping everyone understand Scrum theory and practice, both within the Scrum Team and the organization. The Scrum Master is accountable for the Scrum Team’s effectiveness. They do this by enabling the Scrum Team to improve its practices, within the Scrum framework

 
Geplaatst : 25/02/2024 2:50 pm
Deel: