Forum

Three Scrum Teams a...
 
Meldingen
Alles wissen

Three Scrum Teams are working on the same Product. It is recommended that the teams must merge their code before the Sprint ends

1 Berichten
1 Gebruikers
0 Reactions
179 Bekeken
(@roy-slotboom_pewjck65)
Berichten: 261
Lid Admin
Topic starter
 

Three Scrum Teams are working on the same Product. It is recommended that the teams must merge their code before the Sprint ends

A. True
B. False

Correct Answer: A

The purpose of a Sprint is to create a useful Increment. If the code from multiple teams has not been merged a useful and potentially releasable Increment cant be created. Regardless of how many teams work on the same Product, their code should be merged

 
Geplaatst : 25/02/2024 3:45 pm
Deel: