Which of the following is required by Scrum?

1 Berichten
1 Gebruikers
0 Reactions
96 Bekeken
(@roy-slotboom_pewjck65)
Berichten: 261
Lid Admin
Topic starter
 

Which of the following is required by Scrum?

A. Sprint Retrospective
B. Members must be stand up at the Daily Scrum
C. Sprint Burn-down Chart
D. Release planning
E. All of the above

Correct Answer: A

Of the options offered, only the Sprint Retrospective is required

 