Which output from Sprint Planning provides the Development Team with a target and overarching direction for the Sprint?

A. The Sprint Backlog
B. The Sprint Goal
C. The release plan
D. Sprint Review minutes

Correct Answer: B

The Sprint Goal provides the Development Team with a target for the Sprint. It is the Product Backlog items selected for the Sprint, plus the plan for delivering them

 