Meldingen
Alles wissen
PSM1 Questions with Answers
1
Berichten
1
Gebruikers
0
Reactions
117
Bekeken
Topic starter
Who can abnormally terminate a Sprint?
A. The Scrum Master
B. The Development Team or its members
C. The Product Owner
D. The Stakeholders
Correct Answer: C
Only the Product Owner has the authority to terminate a Sprint, even though this should be avoided at all cost. The Scrum Master can terminate a Sprint only on the Product Owners behalf
Geplaatst : 25/02/2024 3:16 pm