Who can change the Sprint Backlog during a Sprint?

1 Berichten
1 Gebruikers
0 Reactions
113 Bekeken
(@roy-slotboom_pewjck65)
Berichten: 261
Lid Admin
Topic starter
 

Who can change the Sprint Backlog during a Sprint?

A. The Scrum Master
B. The Product owner
C. Stakeholders
D. The Developers

Correct Answer: D

Only the Developers can change the Sprint Backlog during a Sprint, the Product Owner can change the Product Backlog.

 