Meldingen
Alles wissen
PSM2 Questions with Answers
1
Berichten
1
Gebruikers
0
Reactions
198
Bekeken
Topic starter
Successful use of Scrum depends on people behaving and acting in accordance with the Scrum Values.
What might happen if the level of openness reduces? (Select all that apply)
A. Collaboration may become more difficult
B. The quality of the products may reduce
C. Time to market may slow down
D. Stakeholders may lose trust in the Scrum Team
Correct Answer: A,B,C,D
The Scrum Team and its stakeholders agree to be open about all the work and the challenges with performing the work. The level of openness will directly impact the outcomes and value delivered.
Geplaatst : 25/02/2024 6:24 pm