Which statements are correct about scope during a Sprint? (Select 2 answers)
A. Developers focus on finishing all the Sprint Backlog items as agreed in Sprint Planning
B. The Sprint Goal emerges as the Developers work through the Sprint Backlog and learn more about the work
C. Scope may be re-negotiated as more is learned
D. Scope may be clarified as more is learned
Correct Answer: C,D
The Developers modify the Sprint Backlog throughout the Sprint, and the Sprint Backlog emerges during the Sprint. The work and scope of work may be clarified or re-negotiated with the Product Owner where necessary.